California Code of Regulations (Last Updated: August 6, 2014) |
Title 8. Industrial Relations |
Division 1. Department of Industrial Relations |
Chapter 4. Division of Industrial Safety |
Subchapter 5. Electrical Safety Orders |
Group 2. High-Voltage Electrical Safety Orders |
Article 36. Work Procedures and Operating Procedures |
§ 2940.3. Inclement Weather.
Latest version.
- Work on or from structures shall be discontinued when adverse weather, such as high winds, ice on structures, or the progress of an electrical storm in the immediate vicinity, makes the work hazardous, except during emergency restoration procedures.HISTORY1. Amendment of section filed 7-11-96; operative 8-10-96 (Register 96, No. 28).
Note
Note: Authority cited: Section 142.3, Labor Code. Reference: Section 142.3, Labor Code.