§ 1611.3. Disassembly - Additional Requirements for Dismantling of Booms and Jibs (Applies to Both the Use of Manufacturer Procedures and Employer Procedures).  


Latest version.
  • Dismantling (including dismantling for changing the length of) booms and jibs.
    (a) None of the pins in the pendants are to be removed (partly or completely) when the pendants are in tension.
    (b) None of the pins (top or bottom) on boom sections located between the pendant attachment points and the crane/derrick body are to be removed (partly or completely) when the pendants are in tension.
    (c) None of the pins (top or bottom) on boom sections located between the uppermost boom section and the crane/derrick body are to be removed (partly or completely) when the boom is being supported by the uppermost boom section resting on the ground (or other support).
    (d) None of the top pins on boom sections located on the cantilevered portion of the boom being removed (the portion being removed ahead of the pendant attachment points) are to be removed (partly or completely) until the cantilevered section to be removed is fully supported.
HISTORY
1. New section filed 7-7-2011; operative 7-7-2011. Exempt from OAL review pursuant to Labor Code section 142.3(a)(3) (Register 2011, No. 27).

Note

Note: Authority cited: Section 142.3, Labor Code. Reference: Section 142.3, Labor Code.