§ 65628. Application Fees.


Latest version.
  • (a) Each person submitting an offsite treatment facility permit application will be charged a processing fee of one hundred dollars ($100) per hour up to a maximum of fifty thousand dollars ($50,000). The processing fee is to cover costs for technology evaluation, construction inspections, and review of records relative to monitoring procedures and operation. The fee will be billed as follows:
    (1) An initial deposit of twenty-five thousand dollars ($25,000) with the application.
    (2) When the costs for processing the application reach 75 percent of the initial deposit, a second deposit amounting to one-half of the initial deposit shall be paid, and if processing costs exceed 75 percent of the second deposit, the remaining twelve thousand, five hundred dollars ($12,500) shall be charged.
    (3) For subsequent deposits, after the first deposit, the Department shall give 30 days notice by registered mail of the further amount of fee due. If this amount is not received by the Department within the stated 30-day period, the application shall be denied, and there shall be no refund to the applicant.
HISTORY
1. New section filed 10-15-91 as an emergency; operative 10-15-91 (Register 92, No. 7). A Certificate of Compliance must be transmitted to OAL 2-12-92 or emergency language will be repealed by operation of law on the following day.
2. New section refiled 1-23-92 as an emergency; operative 2-12-92 (Register 92, No. 15). A Certificate of Compliance must be transmitted to OAL 6-11-92 or emergency language will be repealed by operation of law on the following day.
3. Certificate of Compliance as to 1-23-92 order including amendment of section transmitted to OAL 6-2-92 and filed 7-14-92 (Register 92, No. 29).
4. Editorial correction of History 2 (Register 95, No. 47).

Note

Note: Authority cited: Sections 208 and 25017, Health and Safety Code. Reference: Sections 25036, 25079, 25079.1, 25079.2 and 25079.3(b), Health and Safety Code.